DMC Computer Center
Remodel
December 2010
On the weekend of Dec 22, 2010, the DMC computer room was completely
shutdown so that all servers, networking, and storage devices could be
put into new racks and supplied with 10GbE internet.
The process took 4 people two days and nights, since there are over
60 servers. We installed 10 new Dell 48-core server machines,
so that we could initiate the migration to a new virtualized environment.

The pictures illustrate the before, during, and after. In the before
picture, the wiring and electrical had become a complicated mess of routing
and spaghetti. The new organization took all of the networking from underneath
the floor and move it overhead where it is well-tagged, and much more
manageable. All services were restored after 36 hours and work continues
on getting all services wired with much higher capacity 10Gb ethernet.

Wiring is well organized and easy to track in the new
installation.

Computer center back up and running, All services were restored
after 36 hours.
vol13
no1 | Next article
Submitted by Rick Benson, IRIS DMC
|